Tuesday, December 3, 2013

Next Step Group Home Construction Update

Here’s an update on the construction of Imagine!’s Next Step Group Home.

Yesterday and early today, forms were set to pour the foundation walls. Late-morning today the concrete was poured, and the concrete work for walls was wrapped up mid-afternoon. Once the foundation walls were poured, the site was covered with thermal blankets due to the extreme cold forecasted to arrive. The thermal blankets will be in place for two to three days to allow the concrete walls to set and dry in the forms. Once the forms are dry, they will be removed, and the next steps will be for rough-in plumbing in the basement, setting the rebar for the basement slab, and, following a bunch on inspection, framing will begin.

 
 
 
 
 
 